TechUS Air Force to phase in $141 (£109) bn sentinel missile by 2031

US Air Force to phase in $141 (£109) bn sentinel missile by 2031

By the decade's end, the United States Air Force will introduce the new intercontinental ballistic missile LGM-30A Sentinel into service. It is designed to replace the ageing Minuteman family of missiles. This programme is one of the critical components for the future of American strategic nuclear deterrence, forming the land-based foundation of the nuclear triad.

Minuteman missile test
Minuteman missile test
Images source: © East News | AP

In addition to land-based ballistic missiles, the Americans also have shorter-range ballistic missiles launched from specially designed nuclear-powered submarines. They also have an air component in the form of atomic bombs (technically thermonuclear) and cruise missiles with nuclear warheads.

From Minuteman to Sentinel

The Minuteman family of missiles has been in service since 1962, with the current version being the LGM-30G Minuteman III (its first version entered service in 1970). It is the only variant used by the US Air Force (USAF), which is responsible for the triad's land and air components.

Intercontinental missiles produced by Boeing range up to 14,000 kilometres and reach an altitude of 1,100 kilometres. In the final phase of flight, the third stage can reach up to 28,000 kilometres per hour. The Minuteman III is equipped with the MIRV system, allowing it to carry more than one (up to three) warhead carrier (reentry vehicle RV) and launch them independently in different directions. Their number was limited to one due to the 1993 START II disarmament treaty, although in practice, most Minuteman missiles were not modified until 2010 (and possibly even later).

It's no surprise, since only the USA ratified the treaty. RVs of the Mk 12 type with the W78 warhead and the Mk 21 with the W87 warhead remain in use. Due to their significant size (over 18 metres in length) and weight (approximately 36,000 kilograms), the three-stage missiles are launched from well-protected underground silos.

About 400 missiles arm three missile wings: the 90th, 91st, and 341st. All of them fall under the Global Strike Command (AFGSC). It also oversees the air wings armed with B-2A and B-52H strategic bombers, and soon also the B-21 (and the B-1B, although it doesn't carry nuclear weapons).

In the 1980s, the Minuteman III was anticipated to be replaced by the LGM-118 Peacekeeper, which carried up to 6 RVs with higher accuracy at the time (mean error of around 40 to 90 metres). The missile entered service in 1984 but was withdrawn 21 years later due to the ratification of the START II treaty and budgetary issues. Therefore, the ageing Minuteman IIIs were modernised.

Currently, the GBSD programme, which involves the development of the LGM-35A Sentinel, is underway. This programme is essential due to the expiring lifespans of the Minuteman III missiles (already extended multiple times) and the need to maintain the scientific and production capabilities necessary for building such crucial weaponry for the USA.

The Need for New Weapons

The programme for developing a new missile and modernising silos and command centres began in 2016. Lockheed Martin, Boeing, and Northrop Grumman applied to participate in the project. In 2017, the USAF awarded initial work contracts to the two companies on this list. In 2019, the USAF selected the reentry vehicles and warheads for the new missile: older Mk 21s with the W87 warhead or newer Mk 21As with the W87-1 warhead.

Ultimately, Northrop Grumman remained in the race for the lucrative contract. Boeing withdrew from the project at the end of 2019 because a competitor bought the key rocket engine manufacturer Orbital ATK. The winner had a lot at stake. The contract is valued at $13.3 (£10) billion, and the programme's total value over the first 20 years is expected to reach $63 (£48) billion. By the time the missiles retire from service, which is planned for 2075, this value could rise to $85 (£65) billion.

According to a 2023 GAO report, the missile was supposed to enter service in 2030, a year later than anticipated. However, the programme's costs were expected to stay within the planned budget. The USAF quickly debunked this optimistic thesis, as by January 2024, it was known that the total costs had risen to $125 (£97) billion, and the delay had increased to two years. According to the Department of Defense, the costs were estimated at nearly $141(£109) billion in July.

Mysterious American missile

Little is known about the missile itself today. Based on disclosed information, the USAF plans to purchase 642 production missiles, 400 of which will enter operational service, replacing the ageing Minuteman IIIs. The remaining missiles will serve as reserves or be used in tests and exercises. According to current plans, initial operational readiness will be achieved no earlier than 2031, which means the deployment of the first nine missiles in silos. Unless things change, the USAF is expected to receive one missile per week for about nine years.

Full operational readiness was initially projected for 2036 (after deploying 400 missiles), so today, we can probably talk about 2038. In parallel, virtual prototypes and physical versions of future missile components are being tested.

Not all tests are successful; for example, on 6 July 2022, a Minotaur II+ rocket exploded 11 seconds into flight with a Mk 21A reentry vehicle on board. Despite this, most components have already been developed, although some still require minor adjustments. Wind tunnel and engine tests are also being conducted, and preliminary work is underway on the successor to the Mk 21 family of RVs, tentatively called the NGRV.

During a speech at the Mitchell Institute, Major General Andrew Gebara, Deputy Chief of Staff for Strategic Deterrence and Nuclear Integration, declared that the USAF does not want to slow down or stop the programme. However, he indicated that the programme requires restructuring, as the costs of the LGM-35A programme have already increased by half.

Work on the successor to the Minuteman III is progressing well; if there are any issues, they do not seem impossible. Until the restructuring is completed, there is no talk of achieving the so-called Milestone B, i.e., setting the final budget and schedule for the programme, based on which the contractor would continue the work. This could mean further delays and the need to keep the Minuteman missiles in service. However, it seems that the Sentinel programme remains secure, although its future may be somewhat rocky.

Related content
© Daily Wrap
·

Downloading, reproduction, storage, or any other use of content available on this website—regardless of its nature and form of expression (in particular, but not limited to verbal, verbal-musical, musical, audiovisual, audio, textual, graphic, and the data and information contained therein, databases and the data contained therein) and its form (e.g., literary, journalistic, scientific, cartographic, computer programs, visual arts, photographic)—requires prior and explicit consent from Wirtualna Polska Media Spółka Akcyjna, headquartered in Warsaw, the owner of this website, regardless of the method of exploration and the technique used (manual or automated, including the use of machine learning or artificial intelligence programs). The above restriction does not apply solely to facilitate their search by internet search engines and uses within contractual relations or permitted use as specified by applicable law.Detailed information regarding this notice can be found  here.